Project includes 51-mile stretch that will touch Kosciusko and McAdams
Entergy and C Spire are teaming up on an $11 million fiber infrastructure project spanning over 300 miles in 15 Mississippi counties that will open the door for future delivery of a wide variety of next-generation broadband services to consumers and businesses in some of the most isolated and rural parts of the state.
The construction project will involve placing fiber optic cable along five separate routes as follows:
Delta: a 92-mile route through Sunflower, Humphreys, Madison and Hinds counties and near the cities of Indianola, Inverness, Isola, Belzoni, Silver City, Yazoo City, Bentonia, Flora and Jackson.
North: a 51-mile stretch in Attala, Leake and Madison counties, including near the towns of McAdams, Kosciusko and Canton.
Central: a 33-mile route through Madison, Rankin and Scott counties and near the towns of Canton, Sand Hill and Morton.
South: a 77-mile route passing through Simpson, Jefferson Davis, Lawrence and Walthall counties and near the towns of Magee, Prentiss, Silver Creek, Monticello and Tylertown.
Southwest: a 49-mile stretch in Franklin and Adams counties that’s near the communities of Bude, Meadville, Roxie, Natchez and Eddiceton.
The project is the brainchild of Brandon Presley, chairman of the state Public Service Commission, and has been on the drawing board for over two years. The massive infrastructure project, one of the largest in the nation, received a final “green light” when the PSC approved an order Tuesday, Feb. 6 authorizing the work to begin later this spring.Project includes 51-mile stretch that will touch Kosciusko and McAdams
Entergy and C Spire are teaming up on an $11 million fiber infrastructure project spanning over 300 miles in 15 Mississippi counties that will open the door for future delivery of a wide variety of next-generation broadband services to consumers and businesses in some of the most isolated and rural parts of the state.
The construction project will involve placing fiber optic cable along five separate routes as follows:
Delta: a 92-mile route through Sunflower, Humphreys, Madison and Hinds counties and near the cities of Indianola, Inverness, Isola, Belzoni, Silver City, Yazoo City, Bentonia, Flora and Jackson.
North: a 51-mile stretch in Attala, Leake and Madison counties, including near the towns of McAdams, Kosciusko and Canton.
Central: a 33-mile route through Madison, Rankin and Scott counties and near the towns of Canton, Sand Hill and Morton.
South: a 77-mile route passing through Simpson, Jefferson Davis, Lawrence and Walthall counties and near the towns of Magee, Prentiss, Silver Creek, Monticello and Tylertown.
Southwest: a 49-mile stretch in Franklin and Adams counties that’s near the communities of Bude, Meadville, Roxie, Natchez and Eddiceton.
The project is the brainchild of Brandon Presley, chairman of the state Public Service Commission, and has been on the drawing board for over two years. The massive infrastructure project, one of the largest in the nation, received a final “green light” when the PSC approved an order Tuesday, Feb. 6 authorizing the work to begin later this spring.